please click here.

Republic of Indonesia - Energizing Thousands of Islands

Indonesia is Southeast Asia’s most populous country with a total installed hydro capacity of about 5,258 MW, which means only 6% of the technically feasible hydropower potential is de­veloped so far.

As the government intends to increase rural electrification, micro to small hydropower plants will be required in the years to come. Hydropower plants will play a significant role in the country’s development schemes.

Dam of Cirata hydropower plant

Dam of Cirata hydropower plant

ANDRITZ HYDRO in Indonesia

In 1996, ANDRITZ HYDRO established a subsidiary in the capital of Jakarta, but the company has been active in Indonesia for more than 100 years, with its first de­li­very in 1910 (Bangoen Poerbo). ANDRITZ HYDRO has installed or modernized about 180 units with more than 3,000 MW in Indonesia. This means, more than half of the installed capacity comes from ANDRITZ HYDRO.

HPP Cirata: 

In December 2013, ANDRITZ HYDRO was awarded a contract from PT Pembangkitan Jawa-Bali (PT. PJB) for the supply, installation, and commissioning of a new stator for the Cirata hydropower plant. The Cirata underground power station consists of HPP Cirata I and HPP Cirata II, with a total installed capacity of 1,040 MW. All eight turbine-generator units as well as the complete electro-mechanical equipment were originally supplied by ANDRITZ HYDRO.

Peusangan 1 and 2: 

In August 2013, ANDRITZ HYDRO signed a contract with PT. Perusahaan Listrik Negara (PLN) for the design, supply, and installation of electro-mechanical equipment at these run-of-river hydropower plants. The scope of supply consists of turbines, generators, and associated electrical auxiliaries. HPP Peusangan 1 and Peusangan 2 will have an expected annual output of 327 GWh.

HPP Karebbe: 

ANDRITZ HYDRO received several con­tracts: 2005, the supply and installation of turbines, generators and auxiliaries; 2008, for penstocks and gates; and 2009, for EPS (Electrical Power System).

HPP Larona: 

ANDRITZ HYDRO was assigned the modernization of the Larona hydropower plant in 2008. The scope of supply comprised two generators upgraded from 65 MVA to 85 MVA, replacement of runners and electrical equipment, as well as installation and commissioning services.

HPP Musi: 

In 2004, ANDRITZ HYDRO  was awarded a contract for the supply of turbines and auxiliary equipment for the 210 MW Musi hydropower plant.

For the time being several small hydropower plants are currently under construction such as Cianten 1B, 2 and 3, and Cibalapulang 1, 2 and 3.


The high quality and excellent know-how of ANDRITZ HYDRO equip­ment is demonstrated at HPP Ketenger, for which ANDRITZ HYDRO delivered the original runner in the 1930s. The runner is still in operation to the full satisfaction of the customer.

All these successful orders show the confidence of the customers in ANDRITZ HYDRO’s technology know-how and prove once again ANDRITZ HYDRO´s leading position in Indonesia’s hydropower market.

Unit hall of Cirata hydropower plant

Unit hall of Cirata hydropower plant

INDONESIA FACTS

254.5 Mio.Population
96%Access to electricity
5,258 MWInstalled hydro capacity
1,780 MWHydro capacity under construction
11%Share of generation from hydropower
25,140 GWhHydro generation
401,646 GWhTechnically feasible hydro generation potential                        


Hydropower & Dams World Atlas 2015 and The World Bank

Mytigne River near Deedoke hydropower plant

Next article

Republic of the Union of Myanmar - Hydropower for a Moving Country

Read more

List of all articles

All content of HYDRO NEWS ASIA - Special edition

Read more
Contact us
HYDRO News Editorial Office
Eibesbrunnergasse 20
1120 Vienna
downloads
  • Article as PDF PDF : 296 KB
  • HYDRO News Asia PDF : 7.1 MB